In order to meet the needs of growing pupil numbers Cams Hill School commissioned Axis Architecture to develop a proposal to be taken forward, with planning permission granted, to receive state funding. This would be the 4th major design to completion project Axis has provided Cams Hill School.

Under floor heating was installed throughout the building allowing for free use of spaces. Removable walls were also introduced to break up spaces and connect them for various purposes such as exams or events.

The school required six permanent classrooms, an exam hall, two offices, two mentoring rooms and a medical room.

Client: Cams Hill School

Architects: Axis Architecture Ltd

Structural Engineer: Cowan Consultancy

Main Contractor: LST Building Services

Project Manager: Malcolm Osman Building

Contract value: £1.4m

Project Duration: 12 months – complete November 2016